The Section 20 Consultation Process and Timeline, Stage by Stage
The procedure depends on the type of works or agreement, but for many privately procured works it follows the stages below - here's what's normally expected, and what's worth checking.
Written and checked by the Section 20 Defender team · Last reviewed 29 October 2026 · How we check our guides
New to Section 20? Start with Section 20 Notices Explained, our overview guide.
Unfamiliar term? See the Section 20 glossary.
The short answer
Under the ordinary procedure for privately procured major works, consultation normally has two stages before the contract is signed, and sometimes a third afterwards. A Notice of Intention invites written observations within 30 days beginning with the date of the notice. A Statement of Estimates then sets out the estimates obtained, normally at least two. In some procedures, a Notice of Reasons explains the contract award. Long-term agreements and public-notice procurement follow different rules.
How this process varies
The required procedure depends on whether the proposal concerns qualifying works or a qualifying long-term agreement, whether the works are being carried out under an existing long-term agreement, and whether the landlord is required to use a public-notice procurement process. The stages below describe the ordinary procedure used for privately procured qualifying works - see “Long-term agreements work differently” below for how the documents and requirements change for a qualifying long-term agreement.
The ordinary procedure at a glance
A simple flowchart of the usual order for privately procured qualifying works. Real timescales are often longer, the dates on your own notices take priority, and long-term agreements and public-notice procedures follow different steps.
1. Notice of Intention
Describes the works and the reasons for them, invites written observations and invites contractor nominations.
2. First observation period
30 days beginning with the date of the notice. Observations and nominations go in during this period.
3. Estimates obtained
Normally at least two, at least one from a contractor wholly unconnected with the landlord, plus any nominee’s estimate obtained.
4. Statement of Estimates
Sets out the estimates, summarises earlier observations and the landlord’s responses, and says where all the estimates can be inspected.
5. Second observation period
30 days beginning with the date of the statement. The landlord must have regard to observations made in time.
6. Contract entered into
The landlord chooses the contractor.
7. Notice of Reasons, if needed
Normally within 21 days of the contract, where the contractor is neither a nominee nor the lowest estimate.
Stage one: the Notice of Intention
This is generally the first document a leaseholder sees. It normally describes the works the landlord is proposing, the reasons for them, and invites written observations within the statutory observation period - 30 days beginning with the date of the notice. Where the applicable procedure allows it, it also invites leaseholders to nominate a contractor from whom the landlord should try to obtain an estimate. Where the proposed contract is subject to a public-notice procurement process, leaseholders don’t have that nomination right. Worth checking: does the notice actually describe the works clearly enough to understand what’s being proposed, does it explain how to make observations, and does it provide the required observation period, normally 30 days? Our observation deadline calculator works out the usual last day from the date of the notice; the end date printed on the notice itself takes priority.
If you want to nominate a contractor, our free request letter templates include an editable nomination letter. It has to reach the landlord within the observation period.
Stage two: the Statement of Estimates
Under the ordinary procedure, the landlord normally obtains and presents at least two estimates, including one from a contractor unconnected with the landlord. If a valid leaseholder nomination was made and an estimate was obtained from that contractor, it should normally be included. Different requirements can apply where the proposed contract is subject to a public-notice procurement process. A Statement of Estimates is normally issued setting these out, along with a summary of any observations received and the landlord’s response to them. Worth checking: were the estimates actually obtained from more than one contractor, was a valid nomination genuinely considered, and were leaseholder observations addressed rather than simply logged?
Our guide on how to read a statement of estimates walks through a fictional example and the questions worth asking.
After the contract is awarded: the Notice of Reasons
In some procedures, the landlord must give affected leaseholders a written statement of its reasons for choosing the contractor. This applies where the contractor was neither nominated by leaseholders or a recognised tenants’ association nor submitted the lowest estimate. The statement is generally due within 21 days of entering into the contract. This is an explanation of the award decision, not a further opportunity to nominate contractors or submit observations before the contract is entered into. Worth checking: was a Notice of Reasons actually issued when it looks like it should have been, and does it give a genuine explanation rather than a generic statement?
What happens if a stage seems to have been skipped or rushed
It’s worth building a timeline of exactly what you received and when, and asking your landlord or managing agent directly about anything that looks missing or out of order. Our guide on writing an effective observation letter covers how to do that clearly. It’s important to understand that even a genuine consultation shortfall doesn’t automatically mean a cost is avoided. If the landlord failed to comply, the amount it can normally recover is limited to £250 (or £100 per accounting period for a qualifying long-term agreement). But it can apply to the First-tier Tribunal for dispensation from some or all of the requirements (dispensation isn’t available for certain building-safety remediation works), which our dispensation applications guide explains in more detail. Whether a specific consultation failure actually matters enough to affect what you owe is ultimately a question for a tribunal or a solicitor, not something this guide - or an automated tool - can determine for you.
Long-term agreements work differently
A qualifying long-term agreement is generally an agreement entered into by or on behalf of the landlord or a superior landlord for a term of more than 12 months, subject to statutory exclusions. A lift maintenance or cleaning contract is a common example. These follow a related but different procedure from qualifying works. It normally begins with a Notice of Intention and is followed by a Notice of Proposals setting out information about the proposed agreement and its estimated cost, rather than a Statement of Estimates. Different procedures can apply where public procurement requirements are engaged, and further reasons may have to be given depending on how the contractor is selected. The statutory thresholds that trigger consultation differ between the two - see our guide to qualifying works and the £250/£100 thresholds for the detail. Our guide to long-term agreements and public-notice consultation sets out how each of these other procedures works.
Building your own record
Whatever stage you’re at, the most useful thing you can do is keep every notice, letter, and email together with its date, and note anything you sent back and when. That record is exactly what a Defence Pack turns into a clear, source-referenced chronology alongside the rest of your evidence.
Official sources
- SI 2003/1987, Schedule 4 Part 2 - qualifying works not requiring public notice (legislation.gov.uk)
- SI 2003/1987, regulation 2 - definition of 'relevant period' (legislation.gov.uk)
- SI 2003/1987, Schedule 4 Part 1 - qualifying works requiring public notice (legislation.gov.uk)
- SI 2003/1987, Schedule 1 - consultation for qualifying long term agreements (legislation.gov.uk)
- Landlord and Tenant Act 1985, section 20ZA (legislation.gov.uk)
- LEASE: Qualifying long-term agreements (lease-advice.org)
Links checked 27 October 2026. These are the primary sources this guide summarises - they are not legal advice about your own lease or notice.
Related guides
Ready to build your Defence Pack?
Upload your notice and we’ll organise your evidence against every issue area that applies, then draft a clear observation letter you control.
Build My Defence Pack